Construction loans: draws, inspections and liens

Key points

What changed this week

New page on the preview site as of Nov. 26, 2026. Statutes were read on the Massachusetts Legislature site that day. Nothing on this page depends on a weekly data feed.

Educational only. Not a loan offer, commitment or term sheet, and not legal advice. Every lender sets its own draw rules in the loan documents. Statutes are summarized; read the linked text and talk to your attorney.

How a construction draw works

Most construction and heavy-rehab loans follow the same cycle. The timeline below is the general pattern, not any one lender’s procedure.

  1. Budget and schedule of values

    Before closing

    The borrower and general contractor agree a line-item budget (hard costs, soft costs, contingency, interest reserve) and a schedule of values that splits the contract into payable pieces. The lender underwrites against that budget.

  2. Draw request

    Each draw, often monthly

    The contractor submits a payment application showing work completed to date by line item. AIA Documents G702 (application and certificate for payment) and G703 (continuation sheet) are the industry forms many lenders reference.

  3. Draw inspection

    Before funds go out

    An inspector or construction consultant visits the site and confirms the percentage complete for each line. Stored materials are usually checked separately.

  4. Lien waivers and title update

    With each draw

    The lender collects partial lien waivers for amounts paid (Massachusetts prescribes the form in G.L. c. 254 § 32) and runs a title bring-down to make sure no lien or notice of contract has been recorded ahead of the advance.

  5. Funding less retainage

    After approval

    The approved amount is funded, less any retainage the contract holds back and less prior draws. Monthly interest may be paid from the interest reserve if the loan has one.

  6. Completion, final draw, release of retainage

    At substantial completion

    After the final inspection, certificate of occupancy and final lien waivers, the held retainage is released and the loan is paid off or refinanced.

Draw inspections

The inspection answers one question: is the work the borrower wants paid for actually in place? Inspectors compare the payment application to the site, line by line, and flag anything billed ahead of progress. Expect photos, a check of stored materials, and a test of whether the remaining budget can finish the job. The OCC Comptroller’s Handbook, Commercial Real Estate Lending (Version 2.0, March 2022) (opens in a new tab) sets out what bank examiners expect: disbursements matched to verified progress, budget tracking, and inspection reports supporting each advance.

Holdbacks and retainage

Two different things often get called a holdback. Retainage is a share of each payment the owner holds back from the contractor until the job is finished, so punch-list and warranty items get done. The percentage is set by the construction contract. A lender holdback is loan money that stays undisbursed until a condition is met, such as a permit, a certificate of occupancy or a lease.

Massachusetts builds retainage into the statutory partial lien waiver in G.L. c. 254 § 32 (opens in a new tab): the form lists original contract amount, approved change orders, completed to date, less retainage, total payable, less previous payments and current amount due, and the waiver excludes retainage, pending change orders and disputed claims.

Interest reserves

An interest reserve is a budget line, funded by the loan, that pays monthly interest during construction so the borrower does not write a check each month. It is sized from the expected draw schedule and build time. If construction runs long, the reserve can run out before the project is finished, and the borrower then pays interest out of pocket or rebalances the budget. Bank examiners look at whether reserves are sized realistically and whether they hide a project that is not performing (OCC handbook (opens in a new tab)).

Budget and contingency

A construction budget has hard costs (labor and materials), soft costs (design, permits, legal, insurance, financing) and a contingency line for the unknown. Lenders usually release contingency only through a draw request that moves it to a real line item. For what Massachusetts projects cost per square foot, see Cost to build per square foot.

Change orders

A change order changes the contract price or scope. Lenders generally want to approve any change order that affects the budget, because it can leave the loan short of what it takes to finish. On private Massachusetts projects where the prime contract is $3,000,000 or more (projects with 1 to 4 dwelling units are excluded), G.L. c. 149 § 29E (opens in a new tab) requires a written approval or rejection of a request to increase the contract price within no more than 30 days, or it is deemed approved. The same section caps the periods for payment applications at 30 days to submit, 15 days to approve or reject, and 45 days to pay after approval, and it limits pay-if-paid clauses.

Massachusetts mechanic’s liens and lien waivers

Massachusetts mechanic’s liens run on a three-step clock under G.L. c. 254. Each deadline is the earliest of the events listed.

Swipe for more columns.

Massachusetts mechanic’s lien steps under G.L. c. 254, as in force Nov. 26, 2026
StepWhat it isDeadline (earliest of)Statute
1. Notice of contractRecorded at the registry of deeds by the contractor, subcontractor or supplier60 days after a notice of substantial completion is recorded; 90 days after a notice of termination; or 90 days after last furnishing labor or materialsc. 254 § 2 (opens in a new tab) (general contractor); § 4 (opens in a new tab) (subs and suppliers)
2. Statement of accountRecorded statement of the amount due, with credits90 days after a notice of substantial completion; 120 days after a notice of termination; or 120 days after last furnishing labor or materialsc. 254 § 8 (opens in a new tab)
3. Civil actionSuit to enforce the lien; an attested copy of the complaint is recorded within 30 days of filingWithin 90 days after the statement of account is filedc. 254 § 11 (opens in a new tab); § 5 (opens in a new tab)

Advance lien waivers are void. Under G.L. c. 254 § 32 (opens in a new tab), a contract clause that bars filing a notice of contract or enforcing a lien is against public policy, with listed exceptions that include partial waivers and subordinations given for payment on the statutory form. That is why lenders collect a partial waiver with each draw and a final waiver at the end.

Statute text read on malegislature.gov on Nov. 26, 2026. Deadlines are summarized; confirm against the current text with counsel before relying on them.

Sources

Get The Hard Money Edge Every Monday.

Rates, auctions, costs and rules for Massachusetts investors. Written by Chris Anderson, lending since 1998.