Boston Planning's Article 80 file shows 11 projects board-approved in the last 90 days, totaling 1,106 residential units. The Zoning Board of Appeal typically holds hearings on Tuesdays; some sessions fall on other weekdays. The tracker lists no hearings this week (Nov 23, 2026–Nov 29, 2026). As of Nov 26, 2026, 6:44 a.m. ET. Figures below keep their own source and as-of date.
See also Permitting steps in Boston and Massachusetts towns · City housing data: Worcester, Springfield, Lowell, Brockton, Quincy · Utilities and investor calendar · Boston neighborhoods.
Boston Planning’s development pipeline, City of Boston Zoning Board of Appeal hearings, market-impact measures built from those filings, and Massachusetts zoning tools. Every figure is tied to a public official source and a date.
Figures come from the city's public Article 80 project file. Status, units and dates are as the city recorded them. A board approval is not the same as a building permit or a construction start.
Construction Complete
593
Board Approved
253
Permitted / Under Construction
95
Under Review
46
Letter of Intent
11
Board-approved in the last 90 days
11 projects
1,106 residential units
Swipe for more columns.
| Project | Neighborhood | Type | Units | Approved |
|---|---|---|---|---|
| Dot Block (opens in a new tab) | Dorchester | Large Project | 488 | Oct 15, 2026 |
| 165 Park Drive (opens in a new tab) | Fenway | Large Project | 112 | Oct 15, 2026 |
| 1428 Dorchester Avenue (opens in a new tab) | Dorchester | Small Project | 23 | Oct 15, 2026 |
| 201 Hampden Street (opens in a new tab) | Roxbury | Small Project | 24 | Oct 15, 2026 |
| 201-207 Brighton Avenue (opens in a new tab) | Allston | Large Project | 145 | Oct 15, 2026 |
| 50B Park Street (opens in a new tab) | Dorchester | Large Project | — | Oct 15, 2026 |
| 160 McClellan Highway (opens in a new tab) | East Boston | Large Project | — | Oct 15, 2026 |
| 176 Lincoln Street (opens in a new tab) | Brighton | Large Project | 252 | Sep 17, 2026 |
| Benjamin Franklin Institute of Technology | Nubian Square Campus (opens in a new tab) | Roxbury | Large Project | — | Sep 17, 2026 |
| 2062 Dorchester Avenue (opens in a new tab) | Dorchester | Small Project | 20 | Sep 17, 2026 |
| 697 Cambridge Street (opens in a new tab) | Brighton | Small Project | 42 | Sep 17, 2026 |
Swipe for more columns.
| Project | Neighborhood | Type | Units | Filed |
|---|---|---|---|---|
| 49-51 D Street (opens in a new tab) | South Boston | Large Project | 70 | Nov 3, 2026 |
| 169-177 Cambridge Street (opens in a new tab) | Allston | Large Project | 151 | Oct 30, 2026 |
| 133 Federal Street (opens in a new tab) | Downtown | Large Project | 155 | Oct 30, 2026 |
| 65-79 Wareham Street (opens in a new tab) | South End | Small Project | 38 | Oct 29, 2026 |
| 295 Waldemar Avenue (opens in a new tab) | East Boston | Small Project | 35 | Oct 16, 2026 |
| 1016 Washington Street (opens in a new tab) | Dorchester | Small Project | 22 | Oct 15, 2026 |
| 329 Blue Hill Avenue (opens in a new tab) | Roxbury | Small Project | 40 | Oct 9, 2026 |
| 74 Ashton Street (opens in a new tab) | Dorchester | Small Project | 24 | Oct 9, 2026 |
| 64 Poydras Street (opens in a new tab) | Hyde Park | Small Project | 36 | Oct 8, 2026 |
| 80 Christopher Street (opens in a new tab) | Dorchester | Large Project | 108 | Oct 7, 2026 |
| Reserved Channel Development (opens in a new tab) | South Boston Waterfront | Large Project | 1,050 | Oct 6, 2026 |
| 25 Supertest Street (opens in a new tab) | Charlestown | Large Project | 108 | Oct 6, 2026 |
The Zoning Board of Appeal typically holds hearings on Tuesdays. Refresh this panel after each Tuesday session, and again if the city posts a mid-week agenda change. Dates and cases are from the city's tracker, not a reconstructed calendar. Applicant names are shown only when the tracker lists a business, trust or other entity. Names of individual people are omitted; the address and project description remain.
Hearings this week
0
Nov 23, 2026 to Nov 29, 2026
Next hearing
Dec 3, 2026
Thursday · 7 cases
Next Tuesday hearing
Dec 8, 2026
26 cases
Decisions in the last 30 days
24
20 granted, 0 denied, 4 withdrawn
Swipe for more columns.
| Case | Address | Neighborhood | Type | What is proposed |
|---|---|---|---|---|
| BOA1841459 | 431 Pond ST Jamaica Plain 02130 | Jamaica Plain | Zoning | Entry vestibule and private patio addition to an existing nursing home facility. Work includes interior modifications and renovations to an existing rear patio. [ePlans] |
| BOA1856060 | 359 Princeton ST East Boston 02128 | East Boston | Building | Convert single family to two family, build separation of two apartments, frame, insulation, two full bathrooms, two kitchens, new drywall, plaster, floors and painting, plumbing and electrical |
| BOA1871243 | 410 to 438 Tremont ST Roxbury 02116 | Roxbury | Zoning | Change of Occupancy from Childcare to Educational Institute and Community Center. No work proposed at this time. |
| BOA1880543 | 19 Morey RD Roslindale 02132 | Roslindale | Zoning | This is for a front and rear dormer addition to allow for a habitable MBR, bathroom and office in an existing storage attic. Associated stair and plan changes to access the new space. ZBA approval will be required. |
| BOA1883115 | 115 Melville AV Dorchester 02124 | Dorchester | Zoning | Extend existing front porch roof throughout left elevation as per plans. |
| BOA1883773 | 528 E Fifth ST South Boston 02127 | South Boston | Zoning | Remove existing one story element at the rear of existing 2 and a half story residence. Add addition to the rear on the 2nd and 3rd floor. Existing 1 parking spot in the rear to remain. |
| BOA1888487 | 15 Centre LN West Roxbury 02132 | West Roxbury | Zoning | Demolition of existing garage wall and install new exterior wall. Open up roof of sun room to add a a second floor above. Open up existing roof and frame second floor with with 2x6's for exterior walls and 2x10's rafters and joists. and… |
Swipe for more columns.
| Case | Address | Neighborhood | Type | What is proposed |
|---|---|---|---|---|
| BOA1819243 | 57 Walnut PK 2 Roxbury 02119 | Roxbury | Zoning | Seeking to raze the existing structure (under short form SF#) and erect a new building with fourteen residential units. Project includes 13 reduced to 12 (10/21/26) parking spaces and a bike storage room. eplan -- BOA |
| BOA1836965 | 25A Alabama ST Mattapan 02126 | Mattapan | Zoning | Erect a new 2 residential units with parking and decks. As per plans. e[Plans] filed. |
| BOA1847032 | 8 Norwood ST Dorchester 02122 | Dorchester | Zoning | Erect A FOUR STORY 12 unit multi fam building WITH ELEVATOR ACCESS3.18.2026 Application assigned to FD by M. O'Boyle on 4.1.2026 |
| BOA1855909 | 245R to 247R Gallivan BL Dorchester 02124 | Dorchester | Zoning | Construct a two unit additional dwelling building at the rear of the lot. The building will be accessed from Gallivan Blvd by the existing driveway. There will be two main entrance (one door to each unit) facing Gallivan Blvd. We are not… |
| BOA1860819 | 16 Norwood ST Dorchester 02122 | Dorchester | Zoning | Erect 12 unit multi family 4 story building with 12 covered parking spaces at ground level with elevator access*Application assigned to F. D'Amato 4.1.26**Exisitng strucutre on lot to be razed on a separate reviewed and approved Sf… |
| BOA1860822 | 546 Gallivan BL Dorchester 02124 | Dorchester | Zoning | Change of use from a 1 family and dentist office to a 3-family, extend living space in the basement, renovation and new dormer addition. |
| BOA1862135 | 41R to 41B Chickatawbut ST Dorchester 02122 | Dorchester | Zoning | Construct 4 town homes |
| BOA1879047 | 173 to 177 Maverick ST East Boston 02128 | East Boston | Zoning | THE PROJECT SCOPE WILL FIT OUT THE CORE AND SHELL SPACE OF UNIT 102 AT THE PROPERTY. UNIT 102 WILL BECOME A DENTAL PRACTICE. THE SUITE WILL SHARE AN ACCESSIBLE ENTRY THROUGH THE 173 MAVERICK COMMON VESTIBULE. THE DENTAL PRACTICE WILL… |
| BOA1886437 | 56 Rutland SQ Roxbury 02118 | Roxbury | Zoning | Amendment to add 2 decks to the rear of 56 Alt1821433 |
| BOA1886546 | 174 Boston ST Dorchester 02125 | Dorchester | Zoning | Subdivision to create 2 parcels, Lot A, parcel ID 0703162000) for 174 Boston St. (existing 3-family) & the second lot parcel ID 0703161000 for 67 Harvest Street (6 residential units), in conjunction with ERT1607835. conjunction with… |
| BOA1886554 | 67 Harvest ST Dorchester 02125 | Dorchester | Zoning | Subdivision to create 2 parcels, Lot A, parcel ID 0703162000) for 174 Boston St. (existing 3-family) & the second lot parcel ID 0703161000 for 67 Harvest Street (6 residential units), in conjunction with ERT1607835 conjunction with… |
| BOA1890064 | 51 Gates ST South Boston 02127 | South Boston | Zoning | Raze existing structure on a separate permit, combine parcels 0701262000 and 0701261000 to form a new lot of approximately 4,250 sft to erect a new 3-story, 6 Unit residential building with 8 parking spaces. |
| BOA1894474 | 722 Truman HW Hyde Park 02136 | Hyde Park | Zoning | Raze existing dwelling and erect a six (6) unit residential dwelling with six (6) parking spaces. |
| BOA1896415 | 35 to 37 Walk Hill ST Jamaica Plain 02130 | Jamaica Plain | Zoning | New construction 2 family duplex dwelling with two car attached garage on an existing lot of 18,591 sq ft with GFA 4,588, 3 stories. Two or more dwellings on same lot. In conjunction with 39-41 Walk Hill St; 43 Walk Hill St and 45 Walk… |
| BOA1896417 | 39 to 41 Walk Hill ST Jamaica Plain 02130 | Jamaica Plain | Zoning | New construction 2 family duplex dwelling with two car attached garage on an existing lot of 18,591 sq ft with GFA 4,588, 3 stories. Two or more dwellings on same lot. In conjunction with 35-37 Walk Hill St ERT1851691; 43 Walk Hill St and… |
| BOA1896422 | 43 Walk Hill ST Jamaica Plain 02130 | Jamaica Plain | Zoning | New construction 1 family dwelling on with two car attached garage on an existing lot of 18,591 sq ft with GFA 2,214, 3 stories. Two or more dwellings on same lot. In conjunction with 35-37 Walk Hill ERT1851691; 39-41 Walk Hill St… |
| BOA1896425 | 45 Walk Hill ST Jamaica Plain 02130 | Jamaica Plain | Zoning | New construction single family dwelling with a two car attached garage on an existing lot of 18,591 sq ft with GFA 2,213 sq ft, 3 stories. Two or more dwellings on same lot. In conjunction with 35-37 Walk Hill ERT1851691; 39-41 Walk Hill… |
| BOA1901358 | 156 E ST South Boston 02127 | South Boston | Zoning | Renovation to an existing 2-story single family home to 4-story with a deck on the fourth floor. The building will not have an elevator or be sprinklered. |
| BOA1902702 | 526 E Third ST South Boston 02127 | South Boston | Zoning | Amendment to permit ERT1606403 to remove the parking to create living space. Three Units: Unit 1- 1st level; Unit 2- 2nd Level, Unit 3- 3rd & 4th Level & Roof Deck. This application is an amendment to ERT1606403/ BOA-1652033 decision was… |
| BOA1903130 | 19 Rexhame ST Roslindale 02131 | Roslindale | Zoning | Erect dormers and change occupancy to a three unit residential dwelling. |
| BOA1905278 | 99 Erie ST Dorchester 02121 | Dorchester | Zoning | Change the legal occupancy from a building with six residential units to a building with eight residential units. This is a related to ERT 1222287. We are seeking two additional units for the project.*6 units #ERT1222287/2024 |
| BOA1909297 | 139 to 145 Richmond ST Boston 02113 | Boston | Zoning | Change the legal occupancy from seventeen (17) residential units, restaurant with take-out, office, beauty salon, retail store, wireless communications to twenty (20) residential units, restaurant with take-out, office, beauty salon,… |
| BOA1911248 | 500 Gallivan BL Dorchester 02124 | Dorchester | Zoning | New Construction of a multifamily building consisting of 12 residential units with 18 parking spaces and ground level amenity space for the building |
| BOA1912218 | 670 E Broadway South Boston 02127 | South Boston | Zoning | No record of occupancy, Confirm occupancy as Baber Shop and change to Yoga and Fitness. Interior renovation of an existing 1,400 SF barber shop into a yoga and fitness studio, including demolition, new partitions, finishes, MEP… |
| BOA1915465 | 150R William F McClellan HW East Boston 02128 | East Boston | Zoning | Updated scope of work provided via email 10/29/2026: The project site is located at 150R McClellan Highway, East Boston, Massachusetts (a/k/a 160 McClellan Highway), comprises approximately 144,961 square feet (approximately 3.33 acres),… |
| BOA1915469 | 581 to 599 Chelsea ST East Boston 02128 | East Boston | Zoning | Please see ERT1910944 of record for 150R McClellan Highway. Incorporate the ground lease agreement for the proposed use of land to grant abutter the right to construct a portion of building on said land to include ancillary parking and… |
Swipe for more columns.
| Case | Address | Neighborhood | Type | What is proposed |
|---|---|---|---|---|
| BOA1478658 | 799 Columbia RD Dorchester 02125 | Dorchester | Zoning | Proposed Curb Cut. Off-Street Parking of One Vehicle |
| BOA1757827 | 155 to 157 Washington ST Dorchester 02121 | Dorchester | Zoning | Change of occupancy from 24 units and 3 retail stores to 24 units, 2 education centers, and 1art gallery. No work to be done. |
| BOA1823392 | 501 Boylston ST Boston 02116 | Boston | Zoning | New Eversource Electric utility feed from the corner of Newbury St/Clarendon St to building with new Eversource Vault in Subbasement. New manhole will be added on owner's property per Eversource requirement.eplan -- BOA |
| BOA1833187 | 273 Bolton ST South Boston 02127 | South Boston | Zoning | Build proposed 4 story residential unit building*11.5.2026 Revised plans submitted to the ZBA for an updated scope of work prior to the BOA appeals hearing to Build a proposed four story two family dwelling with 3 covered parking spaces |
| BOA1839863 | 841 to 847 Morton ST Mattapan 02126 | Mattapan | Zoning | Demolish the existing structure under SF#, erect a mixed use building for fifty-two (52) residential units, thirty-five (35) parking spaces, ground level uses:1 core and shell Restaurant,1 core and shell Retail and 1 core and shell what?.… |
| BOA1845418 | 606 American Legion HW Roslindale 02131 | Roslindale | Zoning | Legalized existing modular container addition to add 5 trailers to the existing store as storage and accessory office space. (SEE V779251) |
| BOA1849570 | 51 to 59 Stuart ST Boston 02116 | Boston | Zoning | Change existing static off premise sign (authorized via BOA754123 and ALT753628) to include digital format per Article 11-7 within the Theatre District, which authorizes digital format pursuant to a Conditional Use Permit issued by the… |
| BOA1859879 | 3 Navarre PL Hyde Park 02136 | Hyde Park | Zoning | New construction of a single-family residence on vacant land. e[Plans] Filed. |
| BOA1860459 | 16 Russell ST Charlestown 02129 | Charlestown | Zoning | RENOVATION & 2-STORY VERTICAL ADDITION OVER THE EXISTING GARAGE SPACE. ADDING A COUPLE OUTDOOR DECK/BALCONIES. THE BUILDING IS AN EXISTING 3-STORY SINGLE FAMILY HOME. THERE IS NO CHANGE TO THE CURRENT FOOTPRINT & NO CHANGE IN OCCUPANCY. |
| BOA1871184 | 95 Bennett ST Brighton 02135 | Brighton | Zoning | Change of Occupancy from a 2 unit residential building to a 4 unit residential building by way of an addition/interior renovation and parking for 4 vehicles. |
| BOA1872039 | 1 to 5 Savin Hill LN Dorchester 02125 | Dorchester | Zoning | The owner seeks to raze the existing single family home and erect a new 2.5-story, 4-unit residential building with off street parking as per the attached plans. See ALT1684006 for combination of lots. 9th Edition [ePlan filed]. |
| BOA1879201 | 650 VFW PW West Roxbury 02132 | West Roxbury | Zoning | Addition and remodel of existing one-family cape style home. Increase number of bedrooms from three to five and add a family room. |
| BOA1879738 | 20 Ericsson ST Dorchester 02122 | Dorchester | Zoning | Change occupancy to include yacht club. No work to be done. Work done on previous short form. |
| BOA1879853 | 28 Port Norfolk ST Dorchester 02122 | Dorchester | Zoning | Build a new first floor addition and second floor deck to existing residential structure |
| BOA1887120 | 38 Fuller ST Dorchester 02124 | Dorchester | Zoning | Erect new 12 unit residential building, with 12 parking spaces |
| BOA1890420 | 18 Nantasket AV Brighton 02135 | Brighton | Zoning | Updated scope 4/6/2026: Erect a 3 story, 4788sf building with 4 residential units and 5 offstreet parking spaces (4 covered and one in rear of building) on the 5,010sf vacant lot in accordance with the 2021 IBC with 780 CMR (10th edition… |
| BOA1890573 | 797 to 801 River ST Mattapan 02136 | Mattapan | Zoning | Change Occupancy to include Nail School (Professional School). No work done on this permit. Work done on build out (ALT929732) attached hereto. |
| BOA1896320 | 15 Hampstead RD Jamaica Plain 02130 | Jamaica Plain | Zoning | HALF-STORY ATTIC ADDITION AT THE REAR OF THE EXISTING BUILDING AND NEW FRONT DORMER |
| BOA1902360 | 125 to 139 Harvard ST Dorchester 02121 | Dorchester | Zoning | Change occupancy to include restaurant with take out. Install new 10 foot commercial hood. [ePlans] |
| BOA1902542 | 7 to 9 Chelsea ST East Boston 02128 | East Boston | Zoning | Combine parcels (0103873000), (0103871000), (0103870000) and (0103869000), to form one new 18,802 sf.ft lot to be known as 7-9 Chelsea Street and erect a new 84,270 square foot, mixed-use, six-story building containing 120 residential… |
| BOA1903191 | 11 Round Hill ST Jamaica Plain 02130 | Jamaica Plain | Zoning | ADD A FULL 2 SIDED DORMER TO THE TOP LEVEL AS PER PLANS This is currently a single family home with a separate garage. NO RECORD OF OCCUPANCY |
| BOA1917087 | 1698 Centre ST West Roxbury 02132 | West Roxbury | Zoning | CHANGE OCCUPANCY FROM 2 -FAMILY TO PROFESSIONAL OFFICE (DENTAL OFFICE). THE PROPOSED PROJECT SEEKS TO CONSTRUCT AN ADDITION WITH A GROSS SQUARE FOOTAGE CONSISTING OF 326 SF AT THE FIRST FLOOR LEVEL. AT THE BASEMENT LEVEL, THE ADDITION IS… |
Later dates on the tracker: Jan 7, 2027 (6 cases), Jan 12, 2027 (16 cases), Jan 26, 2027 (2 cases), Feb 9, 2027 (2 cases). Case lists for those dates were not included in this refresh.
Swipe for more columns.
| Case | Address | Neighborhood | Decision | Date |
|---|---|---|---|---|
| BOA1920687 | 8 Woodville PK Roxbury 02119 | Roxbury | Withdrawn | Nov 23, 2026 |
| BOA1732278 | 26 Easton AV Hyde Park 02136 | Hyde Park | Granted | Nov 20, 2026 |
| BOA1782691 | 121R River ST Mattapan 02126 | Mattapan | Granted | Nov 20, 2026 |
| BOA1835131 | 7 Helen ST Dorchester 02124 | Dorchester | Granted with proviso | Nov 20, 2026 |
| BOA1838291 | 500 to 510 Truman PW Hyde Park 02136 | Hyde Park | Granted with proviso | Nov 20, 2026 |
| BOA1856369 | 81 Sawyer AV Dorchester 02125 | Dorchester | Granted with proviso | Nov 20, 2026 |
| BOA1870745 | 130 Minden ST Jamaica Plain 02130 | Jamaica Plain | Granted | Nov 20, 2026 |
| BOA1871370 | 4012 Washington ST Roslindale 02131 | Roslindale | Granted | Nov 20, 2026 |
| BOA1886651 | 14 Schuyler ST Dorchester 02121 | Dorchester | Granted with proviso | Nov 20, 2026 |
| BOA1894075 | 31 G ST South Boston 02127 | South Boston | Granted | Nov 20, 2026 |
| BOA1777438 | 68 Theodore Parker RD West Roxbury 02132 | West Roxbury | Granted | Nov 13, 2026 |
| BOA1862299 | 27 Greenwich ST Dorchester 02122 | Dorchester | Granted | Nov 13, 2026 |
| BOA1862338 | 11 Altacrest RD West Roxbury 02132 | West Roxbury | Granted | Nov 13, 2026 |
| BOA1870900 | 22 Harvard ST Charlestown 02129 | Charlestown | Granted | Nov 13, 2026 |
| BOA1870915 | 22 Harvard ST Charlestown 02129 | Charlestown | Granted | Nov 13, 2026 |
| BOA1872919 | 10 to 18 Bowdoin ST Dorchester 02124 | Dorchester | Granted | Nov 13, 2026 |
| BOA1876006 | 23 Linden ST South Boston 02127 | South Boston | Granted | Nov 13, 2026 |
| BOA1879905 | 294 Stratford ST West Roxbury 02132 | West Roxbury | Granted | Nov 13, 2026 |
| BOA1881627 | 55 Brown AV Roslindale 02131 | Roslindale | Granted | Nov 13, 2026 |
| BOA1904468 | 3615 to 3621 Washington ST Jamaica Plain 02130 | Jamaica Plain | Granted | Nov 13, 2026 |
| BOA1837222 | 6 Thacher CT Boston 02113 | Boston | Withdrawn | Nov 12, 2026 |
| BOA1874524 | 28 Goodale RD Mattapan 02126 | Mattapan | Withdrawn | Nov 3, 2026 |
| BOA1874558 | 28 Goodale RD Mattapan 02126 | Mattapan | Withdrawn | Nov 3, 2026 |
| BOA1895407 | 269 E Cottage ST Dorchester 02125 | Dorchester | Granted | Nov 2, 2026 |
Residential units in Article 80 projects with a city status of Board Approved or Permitted / Under Construction, summed by neighborhood. The city file does not publish a completion date, so this is a pipeline count, not a year-by-year delivery forecast.
Swipe for more columns.
| Neighborhood | Board approved | Under construction | Pipeline units | Pipeline projects | Under review |
|---|---|---|---|---|---|
| East Boston | 7,842 | 500 | 8,342 | 27 | 174 |
| South Boston | 1,927 | 2,498 | 4,425 | 30 | 70 |
| Allston | 2,921 | 845 | 3,766 | 30 | 151 |
| Charlestown | 953 | 2,799 | 3,752 | 11 | 108 |
| Dorchester | 2,754 | 588 | 3,342 | 52 | 343 |
| Roxbury | 1,179 | 560 | 1,739 | 28 | 76 |
| Brighton | 1,441 | 240 | 1,681 | 20 | 86 |
| Jamaica Plain | 992 | 635 | 1,627 | 17 | 258 |
| Downtown | 1,155 | 374 | 1,529 | 17 | 200 |
| South Boston Waterfront | 1,085 | 77 | 1,162 | 18 | 1,050 |
| Fenway | 1,098 | 0 | 1,098 | 15 | 157 |
| Mission Hill | 692 | 340 | 1,032 | 13 | 255 |
| Back Bay | 774 | 0 | 774 | 5 | 476 |
| Hyde Park | 537 | 91 | 628 | 10 | 36 |
| Mattapan | 269 | 325 | 594 | 9 | 57 |
| Roslindale | 540 | 49 | 589 | 11 | 0 |
| South End | 384 | 160 | 544 | 11 | 353 |
| West Roxbury | 235 | 101 | 336 | 8 | 44 |
| Longwood Medical Area | 227 | 0 | 227 | 2 | 0 |
| Chinatown | 111 | 110 | 221 | 2 | 47 |
| West End | 152 | 49 | 201 | 8 | 636 |
| Beacon Hill | 0 | 67 | 67 | 1 | 0 |
| Bay Village | 0 | 18 | 18 | 1 | 0 |
| Leather District | 0 | 0 | 0 | 2 | 15 |
| Total of neighborhoods above | 27,268 | 10,426 | 37,694 | 348 | 4,592 |
Pipeline residential units (Article 80 projects that are board-approved or permitted / under construction) divided by renter-occupied housing units in the same neighborhood from the Planning Department's 2025 file (2019–2023 ACS estimates). A neighborhood is flagged when that ratio is at least 10%. This is a supply ratio, not a prediction that rents will rise or fall. Neighborhoods in the Article 80 file that do not have a matching renter count are shown without a ratio. 14 neighborhoods are at or above the 10% of renter-occupied stock threshold.
Swipe for more columns.
| Neighborhood | Pipeline units | Renter-occupied units | Pipeline as share of renter stock |
|---|---|---|---|
| Charlestown | 3,752 | 4,322 | 86.8% |
| East Boston | 8,342 | 13,377 | 62.4% |
| South Boston | 4,425 | 10,175 | 43.5% |
| Downtown | 1,529 | 3,932 | 38.9% |
| Allston | 3,766 | 9,690 | 38.9% |
| South Boston Waterfront | 1,162 | 3,566 | 32.6% |
| Mission Hill | 1,032 | 6,220 | 16.6% |
| Jamaica Plain | 1,627 | 10,481 | 15.5% |
| Roslindale | 589 | 4,825 | 12.2% |
| Hyde Park | 628 | 5,155 | 12.2% |
| Mattapan | 594 | 4,887 | 12.2% |
| Dorchester | 3,342 | 28,225 | 11.8% |
| Back Bay | 774 | 6,574 | 11.8% |
| Roxbury | 1,739 | 15,665 | 11.1% |
| Brighton | 1,681 | 19,930 | 8.4% |
| Fenway | 1,098 | 13,400 | 8.2% |
| Chinatown | 221 | 2,792 | 7.9% |
| West Roxbury | 336 | 4,429 | 7.6% |
| South End | 544 | 10,899 | 5.0% |
| West End | 201 | 4,039 | 5.0% |
| Beacon Hill | 67 | 2,960 | 2.3% |
| Longwood Medical Area | 227 | — | — |
| Bay Village | 18 | — | — |
| Leather District | 0 | — | — |
Status is as listed on the city's November 2026 program presentation. Applicant names of individual people are omitted.
Applications
28
Residential units
2,408
Residential square feet
2.1 million
Swipe for more columns.
| Address | Neighborhood | Units | Inclusionary units | Residential sf | Status |
|---|---|---|---|---|---|
| 281 Franklin St | Downtown | 15 | 3 | 11k | Completed |
| 85 Devonshire St | Downtown | 95 | 17 | 87k | A80 Approved |
| 2 & 5 Longfellow Pl | West End | 24 | 4 | 13k | A80 Approved |
| 1 & 10 Emerson Pl | West End | 33 | 6 | 20k | A80 Approved |
| 615 Albany St | South End | 24 | 4 | 20k | Construction |
| 129 Portland St | Bulfinch Triangle | 25 | 4 | 22k | Construction |
| 95 Berkeley St | South End | 92 | 19 | 80k | Construction |
| 15 Court Sq | Downtown | 80 | 16 | 73k | A80 Approved |
| 263 Summer St | Fort Point | 77 | 15 | 53k | Construction |
| 295 Franklin St | Downtown | 18 | 3 | 14k | Construction |
| 4 Liberty Sq | Downtown | 36 | 6 | 23k | A80 Approved |
| 31 Milk St | Downtown | 98 | 19 | 95k | Construction |
| 10 Liberty/12 Post Office Sq | Downtown | 70 | 12 | 47k | Construction |
| 112 State St | Downtown | 18 | 3 | 14k | Applied |
| 419 Boylston St | Back Bay | 41 | 7 | 35k | A80 Approved |
| One Devonshire | Downtown | 110 | 22 | 112k | A80 Submitted |
| 50 Congress St | Downtown | 169 | 34 | 193k | A80 Approved |
| 1 State St | Downtown | 76 | 13 | 60k | A80 Approved |
| 90 Canal St | Bulfinch Triangle | 75 | 13 | 69k | Applied |
| 294 Washington St | Downtown | 258 | 51 | 185k | A80 Approved |
| 320 Summer St | Fort Point | 145 | 29 | 115k | A80 Approved |
| 11 Ave de Lafayette | Downtown | 70 | 11 | 62k | A80 Approved |
| 59 Meridian St | East Boston | 15 | 3 | 19k | A80 Submitted |
| 15 State St | Downtown | 45 | 8 | 32k | A80 Submitted |
| 65-79 Wareham St | South End | 53 | 9 | 39k | A80 Submitted |
| 105 Beach St | Leather District | 15 | 3 | 11k | A80 Approved |
| 31 St James Ave | Back Bay | 476 | 95 | 454k | A80 Approved |
| 133 Federal St | Downtown | 155 | 31 | 112k | A80 Submitted |
The Article 80 file does not have a separate lab-use field. This list is limited to projects whose published description mentions lab or life-science space.
Swipe for more columns.
| Project | Neighborhood | Gross sf | Residential units | Status |
|---|---|---|---|---|
| 10 Stack Street (opens in a new tab) | Charlestown | 398,725 sf | — | Permitted / Under Construction |
| 125 Lincoln Street (opens in a new tab) | Leather District | 410,000 sf | — | Board Approved |
| Harvard Street Neighborhood Health Center (opens in a new tab) | Dorchester | 45,300 sf | — | Permitted / Under Construction |
| 155 North Beacon Street (opens in a new tab) | Brighton | 611,526 sf | — | Board Approved |
| Seaport Circle Project (opens in a new tab) | South Boston Waterfront | 626,800 sf | — | Board Approved |
| Government Center Garage (East Parcel) (opens in a new tab) | Downtown | 410,000 sf | — | Board Approved |
| 17 Farnsworth Street (opens in a new tab) | South Boston Waterfront | 78,252 sf | — | Board Approved |
| 804-812 Huntington Avenue (opens in a new tab) | Mission Hill | 143,357 sf | 23 | Board Approved |
| 66 Cambridge Street (opens in a new tab) | Charlestown | 1,045,000 sf | — | Board Approved |
| Building 108 (opens in a new tab) | Charlestown | 118,105 sf | — | Board Approved |
| 22 Drydock Avenue (opens in a new tab) | South Boston Waterfront | 433,575 sf | — | Permitted / Under Construction |
| 232 A Street (opens in a new tab) | South Boston Waterfront | 364,315 sf | — | Board Approved |
| 1033-1055 Washington Street (opens in a new tab) | South End | 853,528 sf | — | Board Approved |
| Harvard Enterprise Research Campus (ERC) Phase B (opens in a new tab) | Allston | 1,040,000 sf | 400 | Letter of Intent |
| 645 Beacon Street (opens in a new tab) | Fenway | 497,050 sf | — | Letter of Intent |
| 103 North Beacon Street (opens in a new tab) | Allston | 426,665 sf | — | Board Approved |
| 80 East Berkeley Street (opens in a new tab) | South End | 265,000 sf | — | Permitted / Under Construction |
| Fenway Center - Parcel 7 Air Rights (opens in a new tab) | Fenway | 1,077,000 sf | — | Permitted / Under Construction |
| 1000 Washington Street (opens in a new tab) | South End | 259,999 sf | — | Board Approved |
| 500 Huntington Avenue (opens in a new tab) | Mission Hill | 1,070,895 sf | — | Board Approved |
Alexandria Scraps Fenway Lab Conversion Plans - Bisnow (opens in a new tab)
Google News · Jan 28, 2026
Alexandria Scraps Fenway Lab Conversion Plans Bisnow
Google News · Apr 30, 2026
Fenway lab tower owner optimistic despite loss of major tenant The Business Journals
This is a location list of major Article 80 projects (50 or more residential units, or at least 100,000 square feet) that are board-approved or under construction, shown with MBTA parent stations the city's neighborhood map places in the same neighborhood. It is not an appraisal and it is not a claim that property values will rise.
Swipe for more columns.
| Neighborhood | Major projects | MBTA stations | Station names |
|---|---|---|---|
| Allston | 20 | 6 | Allston Street, Amory Street, Babcock Street, Griggs Street, Harvard Avenue, Packard's Corner |
| Dorchester | 14 | 11 | Ashmont, Butler, Cedar Grove, Fields Corner, Four Corners/Geneva, JFK/UMass, Newmarket, Savin Hill, Shawmut, Talbot Avenue, Uphams Corner |
| Fenway | 13 | 9 | Blandford Street, Boston University Central, Boston University East, Fenway, Kenmore, Lansdowne, Museum of Fine Arts, Northeastern University, Symphony |
| Downtown | 12 | 9 | Aquarium, Bowdoin, Chinatown, Downtown Crossing, Government Center, Haymarket, South Station, State, Tufts Medical Center |
| Brighton | 11 | 8 | Boston Landing, Chestnut Hill Avenue, Chiswick Road, Cleveland Circle, South Street, Sutherland Road, Warren Street, Washington Street |
| South Boston Waterfront | 15 | 3 | Courthouse, Silver Line Way, World Trade Center |
| South Boston | 16 | 2 | Andrew, Broadway |
| Roxbury | 15 | 3 | Massachusetts Avenue, Nubian, Ruggles |
| Mission Hill | 11 | 6 | Back of the Hill, Brigham Circle, Fenwood Road, Mission Park, Riverway, Roxbury Crossing |
| East Boston | 12 | 5 | Airport, Maverick, Orient Heights, Suffolk Downs, Wood Island |
| Jamaica Plain | 9 | 5 | Forest Hills, Green Street, Heath Street, Jackson Square, Stony Brook |
| Charlestown | 9 | 2 | Community College, Sullivan Square |
| Back Bay | 4 | 5 | Arlington, Back Bay, Copley, Hynes Convention Center, Prudential |
| South End | 7 | 0 | |
| Mattapan | 3 | 3 | Blue Hill Avenue, Mattapan, Morton Street |
| Hyde Park | 3 | 3 | Fairmount, Hyde Park, Readville |
| West End | 2 | 3 | Charles/MGH, North Station, Science Park/West End |
| Roslindale | 3 | 2 | Bellevue, Roslindale Village |
| West Roxbury | 3 | 2 | Highland, West Roxbury |
| Beacon Hill | 1 | 2 | Boylston, Park Street |
| Longwood Medical Area | 2 | 0 | |
| Leather District | 2 | 0 | |
| Chinatown | 2 | 0 | |
| Longwood | 0 | 1 | Longwood Medical Area |
Swipe for more columns.
| Project | Neighborhood | Units | Gross sf | Status | Approved |
|---|---|---|---|---|---|
| Allston Yards Building B (opens in a new tab) | Allston | — | 638,500 sf | Board Approved | Dec 12, 2019 |
| 103 North Beacon Street (opens in a new tab) | Allston | — | 426,665 sf | Board Approved | Jan 18, 2024 |
| New Inpatient Building - Franciscan Children's Hospital (opens in a new tab) | Allston | — | 293,000 sf | Board Approved | Oct 10, 2024 |
| 287 Western Avenue (opens in a new tab) | Allston | — | 125,070 sf | Board Approved | Jan 18, 2024 |
| Allston Yards Building C (opens in a new tab) | Allston | 386 | 430,000 sf | Board Approved | Dec 12, 2019 |
| Allston Green (opens in a new tab) | Allston | 349 | 302,500 sf | Permitted / Under Construction | Dec 17, 2020 |
| Allston Square (opens in a new tab) | Allston | 344 | 332,167 sf | Board Approved | Dec 11, 2025 |
| 22-24 Pratt Street (opens in a new tab) | Allston | 318 | 350,500 sf | Board Approved | Jun 13, 2024 |
| 50B Park Street (opens in a new tab) | Dorchester | — | 144,000 sf | Board Approved | Oct 15, 2026 |
| Herb Chambers Honda of Boston (opens in a new tab) | Dorchester | — | 112,600 sf | Permitted / Under Construction | Mar 10, 2022 |
| 35-75 Morrissey Boulevard Phase 1 (75 Morrissey) (opens in a new tab) | Dorchester | 754 | 816,000 sf | Board Approved | Aug 14, 2025 |
| Dot Block (opens in a new tab) | Dorchester | 488 | 421,021 sf | Board Approved | Oct 15, 2026 |
| 800 Morrissey Boulevard (opens in a new tab) | Dorchester | 229 | 279,618 sf | Board Approved | Dec 15, 2022 |
| Willow Baker Development (opens in a new tab) | Dorchester | 191 | 199,671 sf | Permitted / Under Construction | Sep 13, 2021 |
| St. Mary's Center for Women and Children (opens in a new tab) | Dorchester | 122 | 205,135 sf | Permitted / Under Construction | Feb 15, 2024 |
| 115-121 Boston Street (opens in a new tab) | Dorchester | 90 | 113,513 sf | Board Approved | Apr 11, 2024 |
| Fenway Center - Parcel 7 Air Rights (opens in a new tab) | Fenway | — | 1,077,000 sf | Permitted / Under Construction | Mar 12, 2020 |
| 1400 Boylston Street (opens in a new tab) | Fenway | — | 802,000 sf | Board Approved | Feb 15, 2024 |
| Simmons University 2019 IMP Projects (opens in a new tab) | Fenway | — | 498,840 sf | Permitted / Under Construction | Nov 12, 2020 |
| Boston University - Warren Towers Renovation (opens in a new tab) | Fenway | — | 380,200 sf | Permitted / Under Construction | Sep 12, 2024 |
| 262 St. Botolph Street Multipurpose Athletic Facility (opens in a new tab) | Fenway | — | 310,000 sf | Board Approved | Nov 13, 2025 |
| Fenway Corners (North) (opens in a new tab) | Fenway | — | 290,650 sf | Board Approved | Jul 13, 2023 |
| Kenmore Hotel (opens in a new tab) | Fenway | — | 243,000 sf | Board Approved | Feb 11, 2021 |
| 60 Kilmarnock Street (opens in a new tab) | Fenway | 454 | 438,406 sf | Board Approved | Feb 13, 2025 |
| Government Center Garage (East Parcel) (opens in a new tab) | Downtown | — | 410,000 sf | Board Approved | Jan 13, 2022 |
| 280-300 Washington Street (opens in a new tab) | Downtown | 255 | 219,200 sf | Board Approved | Mar 19, 2026 |
| 201 Stuart Street-Motor Mart Garage (opens in a new tab) | Downtown | 231 | 731,000 sf | Board Approved | Oct 17, 2019 |
| 50 Congress Street (opens in a new tab) | Downtown | 169 | 205,682 sf | Board Approved | May 14, 2026 |
| South Station Air Rights (opens in a new tab) | Downtown | 166 | 2,522,000 sf | Permitted / Under Construction | Dec 15, 2016 |
| Dock Square Garage (opens in a new tab) | Downtown | 125 | 456,000 sf | Board Approved | Dec 17, 2020 |
| 16-18 Hawley Street (opens in a new tab) | Downtown | 110 | 95,037 sf | Permitted / Under Construction | May 15, 2025 |
| 85 Devonshire Street (opens in a new tab) | Downtown | 95 | 109,400 sf | Board Approved | Jun 12, 2025 |
| 155 North Beacon Street (opens in a new tab) | Brighton | — | 611,526 sf | Board Approved | Jun 12, 2025 |
| St. Elizabeth's Medical Center Parking Garage (opens in a new tab) | Brighton | — | 201,255 sf | Board Approved | Jun 16, 2022 |
| Boston Landing Hotel Project (opens in a new tab) | Brighton | — | 139,150 sf | Permitted / Under Construction | Jun 16, 2022 |
| 83 Leo M. Birmingham Parkway (opens in a new tab) | Brighton | 333 | 363,150 sf | Board Approved | Apr 10, 2025 |
| 176 Lincoln Street (opens in a new tab) | Brighton | 252 | 1,072,700 sf | Board Approved | Sep 17, 2026 |
| 250 Everett Street (opens in a new tab) | Brighton | 240 | 294,250 sf | Permitted / Under Construction | Jan 16, 2025 |
| 15 Washington Street (opens in a new tab) | Brighton | 229 | 394,637 sf | Board Approved | Dec 7, 2023 |
| 500 Western Avenue (opens in a new tab) | Brighton | 116 | 147,169 sf | Board Approved | Aug 17, 2023 |
| Parcel X (310 Northern Avenue) (opens in a new tab) | South Boston Waterfront | — | 809,260 sf | Board Approved | Nov 17, 2022 |
| Seaport Square - Block G (opens in a new tab) | South Boston Waterfront | — | 650,000 sf | Board Approved | Dec 15, 2022 |
| Seaport Circle Project (opens in a new tab) | South Boston Waterfront | — | 626,800 sf | Board Approved | Jul 14, 2022 |
| 88 Black Falcon Avenue (opens in a new tab) | South Boston Waterfront | — | 571,500 sf | Board Approved | May 11, 2023 |
| Seaport Square - Block D (opens in a new tab) | South Boston Waterfront | — | 499,400 sf | Board Approved | Nov 16, 2017 |
| 22 Drydock Avenue (opens in a new tab) | South Boston Waterfront | — | 433,575 sf | Permitted / Under Construction | Mar 13, 2025 |
| Seaport Square - Block N (opens in a new tab) | South Boston Waterfront | — | 422,000 sf | Permitted / Under Construction | Nov 14, 2019 |
| 232 A Street (opens in a new tab) | South Boston Waterfront | — | 364,315 sf | Board Approved | May 16, 2024 |
| 776 Summer Street - Phase 1 (opens in a new tab) | South Boston | — | 746,000 sf | Board Approved | Jan 19, 2023 |
| 65 Ellery Street (opens in a new tab) | South Boston | — | 708,900 sf | Board Approved | Apr 11, 2024 |
| 505 Dorchester Avenue (Dot Ave) (opens in a new tab) | South Boston | — | 487,400 sf | Board Approved | Apr 11, 2024 |
| 75 Ellery Street (opens in a new tab) | South Boston | — | 464,700 sf | Board Approved | Apr 11, 2024 |
| 246-248 Dorchester Avenue (opens in a new tab) | South Boston | — | 106,500 sf | Board Approved | Dec 12, 2024 |
| Mary Ellen McCormack Redevelopment (opens in a new tab) | South Boston | 1,310 | 1,641,300 sf | Permitted / Under Construction | Dec 14, 2023 |
| Washington Village (opens in a new tab) | South Boston | 746 | 1,000,400 sf | Permitted / Under Construction | Jan 16, 2020 |
| 776 Summer Street - Phase 2 (opens in a new tab) | South Boston | 636 | 1,410,581 sf | Board Approved | Jun 18, 2026 |
| 840 Columbus Avenue (opens in a new tab) | Roxbury | — | 441,100 sf | Permitted / Under Construction | Mar 14, 2024 |
| 716 Columbus Avenue (opens in a new tab) | Roxbury | — | 124,000 sf | Board Approved | Mar 14, 2024 |
| 134 Hampden Street (opens in a new tab) | Roxbury | — | 108,806 sf | Board Approved | May 15, 2025 |
| Drexel Village (opens in a new tab) | Roxbury | 217 | 278,133 sf | Board Approved | Apr 16, 2026 |
| 135 Dudley Street (opens in a new tab) | Roxbury | 170 | 328,338 sf | Board Approved | Aug 19, 2021 |
| 45 Townsend Street (opens in a new tab) | Roxbury | 165 | 179,667 sf | Board Approved | Aug 13, 2026 |
| Doris Bunte Apartments (opens in a new tab) | Roxbury | 164 | 121,640 sf | Permitted / Under Construction | Jul 13, 2023 |
| Parcel 10 - Madison Tropical (opens in a new tab) | Roxbury | 126 | 229,434 sf | Board Approved | May 12, 2022 |
| 500 Huntington Avenue (opens in a new tab) | Mission Hill | — | 1,070,895 sf | Board Approved | Sep 12, 2024 |
| Pike Residence Hall (opens in a new tab) | Mission Hill | — | 235,900 sf | Permitted / Under Construction | Feb 12, 2026 |
| 80-100 Smith Street (opens in a new tab) | Mission Hill | 218 | 269,968 sf | Board Approved | Jan 16, 2025 |
| Parcel 25 (Phases 1, 2, 3) (opens in a new tab) | Mission Hill | 180 | 257,701 sf | Permitted / Under Construction | Dec 14, 2023 |
| 775 Huntington Avenue (opens in a new tab) | Mission Hill | 112 | 144,600 sf | Permitted / Under Construction | Sep 15, 2022 |
| 85 Parker Hill Avenue (opens in a new tab) | Mission Hill | 103 | 84,816 sf | Board Approved | Jul 16, 2026 |
| 1558 Tremont Street (opens in a new tab) | Mission Hill | 95 | 74,721 sf | Board Approved | Oct 12, 2023 |
| 110-128R Terrace Street (opens in a new tab) | Mission Hill | 79 | 93,240 sf | Board Approved | Nov 17, 2022 |
| 160 McClellan Highway (opens in a new tab) | East Boston | — | 152,500 sf | Board Approved | Oct 15, 2026 |
| Suffolk Downs Phase 4 (opens in a new tab) | East Boston | 2,000 | 3,891,825 sf | Board Approved | Sep 24, 2020 |
| Suffolk Downs Phase 3 (opens in a new tab) | East Boston | 1,950 | 3,645,675 sf | Board Approved | Sep 24, 2020 |
| Suffolk Downs Phase 2 (opens in a new tab) | East Boston | 1,295 | 1,959,800 sf | Board Approved | Sep 24, 2020 |
| Suffolk Downs Phase 5 (opens in a new tab) | East Boston | 1,170 | 1,363,000 sf | Board Approved | Sep 24, 2020 |
| Suffolk Downs Phase 1 (opens in a new tab) | East Boston | 735 | 1,639,600 sf | Board Approved | Sep 24, 2020 |
| 1141 Bennington Street (opens in a new tab) | East Boston | 220 | 249,508 sf | Board Approved | Aug 17, 2023 |
| 355 Bennington Street (opens in a new tab) | East Boston | 170 | 193,595 sf | Permitted / Under Construction | Apr 14, 2022 |
| 125 Amory Street Development (opens in a new tab) | Jamaica Plain | 514 | 480,213 sf | Permitted / Under Construction | Dec 16, 2021 |
| 3430 & 3440 Washington Street (opens in a new tab) | Jamaica Plain | 230 | 260,780 sf | Board Approved | Jul 17, 2025 |
| Mildred Hailey Development Building 4 (opens in a new tab) | Jamaica Plain | 179 | 206,000 sf | Board Approved | |
| 539-551 Centre Street (opens in a new tab) | Jamaica Plain | 147 | 136,782 sf | Board Approved | Jun 13, 2024 |
| Mildred Hailey Development Buildings 2 and 3 (opens in a new tab) | Jamaica Plain | 125 | 156,300 sf | Board Approved | Jan 18, 2024 |
| 3390 Washington Street (BMS Paper) (opens in a new tab) | Jamaica Plain | 82 | 155,311 sf | Board Approved | May 11, 2023 |
| 361 Centre Street (Blessed Sacrament) (opens in a new tab) | Jamaica Plain | 55 | 71,934 sf | Permitted / Under Construction | Dec 15, 2022 |
| Rogerson-Beaufort (opens in a new tab) | Jamaica Plain | 41 | 134,960 sf | Board Approved | Jan 15, 2026 |
| 66 Cambridge Street (opens in a new tab) | Charlestown | — | 1,045,000 sf | Board Approved | Mar 14, 2024 |
| 10 Stack Street (opens in a new tab) | Charlestown | — | 398,725 sf | Permitted / Under Construction | Mar 14, 2019 |
| Building 108 (opens in a new tab) | Charlestown | — | 118,105 sf | Board Approved | Sep 18, 2025 |
| Bunker Hill Housing Redevelopment (opens in a new tab) | Charlestown | 2,699 | 3,562,206 sf | Permitted / Under Construction | Oct 16, 2025 |
| One Mystic Avenue (opens in a new tab) | Charlestown | 423 | 289,444 sf | Board Approved | Sep 18, 2025 |
| 201 Rutherford Avenue (opens in a new tab) | Charlestown | 240 | 237,000 sf | Board Approved | Apr 16, 2026 |
| 40 Roland Street (opens in a new tab) | Charlestown | 126 | 945,360 sf | Board Approved | Sep 28, 2023 |
| Austin Street Lots Redevelopment (opens in a new tab) | Charlestown | 123 | 126,000 sf | Board Approved | Oct 16, 2025 |
| 380 Stuart Street (opens in a new tab) | Back Bay | — | 731,000 sf | Permitted / Under Construction | Mar 10, 2022 |
| Belvidere Street Student Housing (opens in a new tab) | Back Bay | — | 250,000 sf | Permitted / Under Construction | Jan 18, 2024 |
| Back Bay/South End Gateway Project (opens in a new tab) | Back Bay | 600 | 1,453,000 sf | Board Approved | Sep 15, 2022 |
| 415 Newbury Street (opens in a new tab) | Back Bay | 133 | 236,681 sf | Board Approved | Dec 14, 2023 |
| Exchange South End (opens in a new tab) | South End | — | 2,089,425 sf | Board Approved | Aug 16, 2018 |
| 1033-1055 Washington Street (opens in a new tab) | South End | — | 853,528 sf | Board Approved | Mar 14, 2024 |
| 17 Bradston Street (opens in a new tab) | South End | — | 352,852 sf | Board Approved | Mar 13, 2025 |
| 80 East Berkeley Street (opens in a new tab) | South End | — | 265,000 sf | Permitted / Under Construction | May 12, 2022 |
| 1000 Washington Street (opens in a new tab) | South End | — | 259,999 sf | Board Approved | Sep 14, 2023 |
| Shawmut Avenue / Washington Street Block Project (opens in a new tab) | South End | 340 | 568,816 sf | Board Approved | Jan 16, 2025 |
| 95 Berkeley Street (opens in a new tab) | South End | 92 | 101,810 sf | Permitted / Under Construction | Nov 13, 2025 |
| Olmsted Village (opens in a new tab) | Mattapan | 284 | 406,530 sf | Permitted / Under Construction | Mar 19, 2026 |
| 1590 Blue Hill Avenue (opens in a new tab) | Mattapan | 105 | 120,262 sf | Board Approved | Aug 13, 2026 |
| 841 Morton Street (opens in a new tab) | Mattapan | 52 | 85,491 sf | Board Approved | Jan 15, 2026 |
| 990 American Legion Highway (opens in a new tab) | Hyde Park | 204 | 341,576 sf | Board Approved | Sep 18, 2025 |
| 1690-1700 Hyde Park Avenue (opens in a new tab) | Hyde Park | 115 | 121,500 sf | Board Approved | Dec 12, 2024 |
| 1702 Hyde Park Avenue (opens in a new tab) | Hyde Park | 68 | 90,115 sf | Board Approved | Apr 16, 2026 |
| MGH Clinical Building (opens in a new tab) | West End | — | 1,748,150 sf | Permitted / Under Construction | Oct 14, 2021 |
| West End Library (opens in a new tab) | West End | 119 | 176,517 sf | Board Approved | May 14, 2026 |
| 3841 Washington Street (opens in a new tab) | Roslindale | 165 | 161,786 sf | Board Approved | Jul 16, 2026 |
| 361 Belgrade Avenue (opens in a new tab) | Roslindale | 124 | 156,865 sf | Board Approved | Mar 16, 2023 |
| 1200 Centre Street (opens in a new tab) | Roslindale | 78 | 95,634 sf | Board Approved | Sep 18, 2025 |
| 100 Charles Park Road (opens in a new tab) | West Roxbury | 121 | 124,996 sf | Board Approved | Nov 16, 2023 |
| 11-26 Heron Street (opens in a new tab) | West Roxbury | 72 | 98,196 sf | Permitted / Under Construction | Jun 13, 2019 |
| 1208C VFW Parkway (opens in a new tab) | West Roxbury | 55 | 62,140 sf | Board Approved | Jan 15, 2026 |
| 33-61 Temple Street (opens in a new tab) | Beacon Hill | 67 | 131,120 sf | Permitted / Under Construction | Apr 10, 2025 |
| 1 Joslin Place Hospital (opens in a new tab) | Longwood Medical Area | — | 736,100 sf | Board Approved | Jun 12, 2025 |
| Longwood Place Phase One (opens in a new tab) | Longwood Medical Area | 227 | 1,423,000 sf | Board Approved | Apr 16, 2026 |
| 125 Lincoln Street (opens in a new tab) | Leather District | — | 410,000 sf | Board Approved | Nov 17, 2022 |
| 2 Financial Center (opens in a new tab) | Leather District | — | 268,400 sf | Board Approved | Dec 12, 2024 |
| 290 Tremont Street (opens in a new tab) | Chinatown | 111 | 130,000 sf | Board Approved | Oct 16, 2025 |
| 49-63 Hudson Street (Parcel R-1) (opens in a new tab) | Chinatown | 110 | 148,877 sf | Permitted / Under Construction | Dec 15, 2022 |
Communities subject to Section 3A
177
Boston is exempt from the Zoning Act, including Section 3A.
Communities in compliance, Attorney General count
165
of 177 subject communities
One hundred seventy-seven communities are subject to Section 3A. Boston is exempt from the Zoning Act, including Section 3A. The Attorney General's January 29, 2026 release said 165 of 177 communities had come into compliance as of that date. That statement is not a substitute for EOHLC's current official status sheet, which could not be downloaded automatically on this refresh. A community is compliant only after EOHLC makes that determination.
Massachusetts Attorney General, press release · Jan 29, 2026
The January 29, 2026 release states that 165 of 177 MBTA Communities had come into compliance as of that date, and that the nine named towns were required to have compliant zoning districts by July 14, 2025.
Edgartown, Edgartown Gardens, LLC (25-06) (opens in a new tab)
Nov 20, 2026
Oak Bluffs, MV Green Villa LLC and Atwood GV, LLC (26-02) (opens in a new tab)
Nov 20, 2026
Falmouth, 85 Brick Kiln LLC (26-03) (opens in a new tab)
Sep 8, 2026
Saugus, 20 Bennett LCC (26-06) (opens in a new tab)
Sep 8, 2026
Raynham, Raynham 44 Development, LLC (24-09) (opens in a new tab)
Jul 22, 2026
Falmouth, West Falmouth Estates, LLC (25-01) (opens in a new tab)
Jul 16, 2026
Chelmsford, Crosby Village, LLC (25-07) (opens in a new tab)
May 20, 2026
Chelmsford, 243 Riverneck, LLC (25-09) (opens in a new tab)
May 20, 2026
Newton, 41 TusNua, LLC (24-13) (opens in a new tab)
Apr 30, 2026
Falmouth, Sandwich Road Housing, LLC (25-12) (opens in a new tab)
Apr 13, 2026
Falmouth, Falmouth Residential, LLC and Northland Residential, LLC (25-11) (opens in a new tab)
Apr 13, 2026
Walpole, Wall Street Dev. Corp. (22-08) (opens in a new tab)
Apr 13, 2026
Google News · Nov 21, 2026
Wilmington faces critical MBTA Communities vote as town seeks to preserve local control Homenewshere.com
Google News · Nov 8, 2026
Dracut Town Meeting to vote on MBTA Communities zoning for third time Lowell Sun
Tewksbury boards approve new MBTA Communities district - Lowell Sun (opens in a new tab)
Google News · Jun 17, 2026
Tewksbury boards approve new MBTA Communities district Lowell Sun
Google News · Mar 26, 2026
Making Room: Newton’s Amy Dain talks impact of MBTA Communities Act, VCOD The Newton Beacon
Google News · May 5, 2026
‘Are we kind of being pricks?’: Resident’s question goes viral as Marblehead passes MBTA zoning The Marblehead Independent
Google News · Jan 16, 2026
MBTA Communities Act Holdouts Are Losing State Funding Streetsblog Massachusetts
Zoning Board rejects proposed Totten Pond Road apartments - Waltham Times (opens in a new tab)
Google News · Apr 16, 2026
Zoning Board rejects proposed Totten Pond Road apartments Waltham Times
Google News · Jun 27, 2025
Developer of key Chestnut Hill site weighs residential 40B if commercial project talks falter Brookline.News
Newton achieves 40B Safe Harbor status - Fig City News (opens in a new tab)
Google News · Jan 9, 2024
Newton achieves 40B Safe Harbor status Fig City News
Google News · Feb 11, 2025
300 apartments proposed in Waltham after lab plan spiked The Business Journals
Google News · Oct 11, 2022
244-unit affordable housing complex planned in Newton: Find out where, what happens next Wicked Local
Google News · Sep 9, 2025
West Main apartment building proposal achieves comprehensive permit at Zoning Board Waltham Times
Statewide tools and inventories. A community’s current Section 3A or SHI status should be confirmed on the official page.
Development pipeline: daily check of the city's Article 80 file (it can change when Boston Planning updates a project). Zoning Board of Appeal: refresh after each Tuesday hearing, and whenever the tracker shows a mid-week agenda change. Office-to-residential list: when Boston Planning posts a new program presentation. Utilities: BWSC rates at each calendar-year change (and after the December 8, 2026 hearing); EIA electricity and gas monthly; EIA heating oil weekly in the heating season; Boston tax rates after the third-quarter bill in late December. Transit and zoning headlines: daily. Investor calendar: daily. MBTA Communities, Housing Appeals Committee, SHI and ADU pages: daily when mass.gov is reachable.
Rates, auctions, costs and rules for Massachusetts investors. Written by Chris Anderson, lending since 1998.
Get the weekly brief every Monday. Subscribe